HST10X

Installation Sequence Pictorial


 
HST10X and enhancement components in the Orbiter Cargo Bay

HST in Normal Berthed Position

HST and enhancement components in the Orbiter Cargo Bay after routine rendezvous, capture, and berthing.
 

The selected mirror configuration is a table-top fold (two-folds) of the 8-m New Primary Mirror (NPM), the New Secondary Mirror (NSM) placed inside the fold of the NPM, and the combination, the New Mirror Assembly (NMA), mounted in an existing Space-Lab Pallet (SLP).

EVA Day 1 - Remove forward section of old light-shield

EVA Day 1. Remove Old Light-Shield section
and install IESS.

EVA Day 2 - Install New Light-Shield

EVA Day 2. Install New Light-Shield using RMS Arm and deploy radially.

EVA Day 3.1 - Install New Mirror Assembly

EVA Day 3.1. Install New Mirror Assembly.

The NMA/OTA interface ring is installed followed
by installation of the NMA using the RMS Arm. 

EVA Day 3.2 - New Light-Shield is deployed radially completing the installation

EVA Day 3.2 The New Light-Shield is deployed axially completing the installation.

 